Development Progress Update | Haus Brandenburg Berlin

15th March 2018

Haus Brandenburg  | An update on progress on site

Haus Brandeburg is an elegant refurbishment of a historic building in fashionable Charlottenburg. Haus Brandenburg is nestled close to major employment hubs and only moments away from Berlin’s most famous shopping boulevard – Kurfürstendamm.

With completion firmly on the horizon, Peter Wheeler from our Berlin office took a trip to Charlottenburg to bring an update on progress on site at Haus Brandenburg.

There are currently two sets of contractors working on site simultaneously and so it really is all systems go.
All the new beams have been put in. They are working on levels 5 and 3 at the moment and work will start on level 4 quite soon.
The mains pipework for hot, cold and waste water has also already been installed running through the building and the heating system will be installed this month.
The building is now sealed with the new roof and new windows throughout.

Most progress has been made on level 5, with all internal stud walls and ceilings already in and layouts are right on spec, with areas for washing machines in the kitchens or in special utility rooms.

All in all, progress is being made at good pace. It’s a fantastic building with many so many beautiful original features.

 